The daily traffic volume along the B10 from Zuffenhausen to Hedelfingen is high. Over the last few years and decades, the route - such as at the Pragsattel - has been successively adapted to this challenge. The last remaining bottleneck is one of Stuttgart’s central junctions on the Neckar - the B10/B14 connection at Leuze, the so-called Leuze junction. The Rosenstein Tunnel road construction project will eliminate this bottleneck and at the same time relieve the residential areas in the surrounding districts of through traffic.
The traffic project consists of two construction phases:
- the construction of the B10 Rosenstein Tunnel and
- the conversion of the B10/B14 connection at the Mineralbad Leuze.
The B10 Rosenstein Tunnel went into operation on March 26, 2022, and work on the Leuze junction is due to be completed by mid-2026. This will allow the road construction project to take full effect. Traffic will then flow along the B10 and, thanks to the tunnel, no longer through Neckartalstrasse and Pragstrasse. A little further upstream, the rebuilt Leuze junction will ensure that traffic flows more smoothly. The conversion of the Leuze junction and the construction of the new Rosenstein tunnel will result in improvements for cyclists and pedestrians and new green spaces will be created, for example on the banks of the Rosenstein in front of the entrance to Wilhelma.
The Leuze node
With a total of seven tunnel tubes, the Leuze junction connects the B10 and B14 federal highways. It is crossed by 120,000 vehicles every day and therefore plays a central role in the flow of traffic between the Neckar valley and the Stuttgart basin. The reconstruction of the Leuze junction will unbundle the traffic flows along the B10 and into the city centre and optimize the traffic flow. The aim is not only to improve the efficiency of this key junction, but also to bring the safety technology up to date. With the start of road construction work on the former B14 turning point, the overall project is entering the home straight. The following construction work will be carried out at the junction until it goes into operation in mid-2026:
First fluorescent tube
Dismantling B14 turner
Wilhelma ramp
Completion of total node
Completed construction work
All traffic control during the construction work will be carried out in cooperation with the Integrated Traffic Control Center (IVLZ). To ensure that traffic can flow as smoothly as possible, individual lanes will only be closed during low-traffic periods, for example at night and at weekends. The short-term closures will be coordinated with the IVLZ to avoid overlaps with major events in Neckarpark, for example.
Changed traffic routing
With the conversion of the Leuze junction, the previous B14 U-turn will no longer be required from October 2022 and the routing of the two main roads B10 and B14 from the junction with Poststrasse will change.
The new traffic routing has created the necessary construction site for the construction of the left-turn ramp for traffic coming from the Rosenstein Tunnel onto the König-Karls-Brücke in the direction of Bad Cannstatt after completion. The traffic routing is expected to remain in place until fall 2025.
B10 and B14 from the direction of Esslingen
B14 in the direction of Stuttgart-Zentrum
B10 from direction Pragsattel
Poststrasse access and exit
The B10 Rose Stone Tunnel
However, the central construction project is the B10 Rosenstein Tunnel, which was opened on March 26, 2022. Within ten years, two tunnel tubes were dug, each carrying two lanes of traffic. Two new technical centers were built. Cross-passages were also built. These cross-connections between the main tubes serve as escape routes. In the event of an emergency, people can use them to get to safety in the other tube.
Equipped with state-of-the-art operating and safety technology, the Rosenstein Tunnel forms the central link between the intersection at Leuze and Löwentor. At 1,300 meters, the tunnel passes under Rosenstein Park and parts of the Wilhelma zoological and botanical gardens.
The completed Rosenstein Tunnel opens up many new opportunities for the adjacent city quarter. Road lanes in Pragstrasse and Neckartalstrasse are being reduced and the space gained has been redesigned since March 2025: Gradually, new cycle paths and footpaths, green spaces and thus also a better connection to the banks of the Neckar directly in front of the entrance to Wilhelma are being created.
Road construction project videos
The Rosenstein Tunnel road construction project is being accompanied by intensive public relations work to keep citizens regularly informed about the current status. Two videos provide an insight into Stuttgart’s largest road construction project, its benefits for pedestrians and cyclists, adjacent residential areas and the banks of the Neckar:
Around the construction project
Traffic planning
New footpath and cycle path
Modern traffic control
Modernization of the main water collector
Municipal Council Printed Matter
Data and facts
Frequently asked questions
Answers to the most important questions about the Rosenstein Tunnel road construction project can be found in the FAQ.